In Project Server 2007, after creating a project using PSI and calling
ReadProject, the ProjectResourceCustomFields table stays empty even
though resources that have custom fields defined and set for them
appear in the ProjectResources table.
To workaround this issue, I tried to manually add these custom fields,
but I'm getting a ResourceCannotUpdateEnterpriseResource error when
running QueueUpdateProject.
when I create the project team with RES_IS_ENTERPRISE_RESOURCE=false
the...
Read more