Importing new start and finish dates

I have written a macro which imports new values from an Excel spreadsheet into the start and finish dates on a project.

If I update a date manually it warns if the date is on a non-working day (the weekend or something). When I run the macro it doesn't bother warning me just overwrites the date and dependency dates even if they are on a weekend.

Is there a setting that allows me to stop this from occurring? I would like the original date to be shown with a warning shown on the problem date...